NGCP, CENECO Set Power Interruptions

The National Grid Corporation of the Philippines (NGCP) is scheduling a power service interruption along Bacolod–San Enrique 69kV transmission line tomorrow, November 7, 2015, Saturday, from 8:00AM to 5:00PM.

Central Negros Electric Cooperative, Inc. (CENECO) shall take advantage of this downtime by implementing simultaneous maintenance activities.

Date: November 7, 2015 - Saturday

Time: 8:00AM to 5:00PM

Reasons:

· NGCP will conduct replacement of corroded LWST at structure no. 96, 139 and 157;

CENECO Sets Power Interruption Today

Central Negros Electric Cooperative, Inc. (CENECO) informs its electricity consumers that, in order to ensure stability of its distribution lines, maintenance activities will be conducted today, November 4, 2015, Wednesday, as follows:

Date: November 4, 2015 - Wednesday

Time: 8:00AM to 5:00PM

Reasons: Replacement of rotten primary poles covering Talisay Feeder 3; and Tree trimming covering Talisay Feeder 3.

Areas Affected:

CENECO Sets Power Interruption on Oct. 31

Central Negros Electric Cooperative, Inc. (CENECO) informs its electricity consumers that, in order to ensure stability of its distribution lines, maintenance activities will be conducted on October 31, 2015 (Saturday), as follows:

Date : October 31, 2015 - Saturday

Time : 8:00AM to 5:00PM

Reasons:

· Replacement of rotten primary poles covering Silay-Lopez Feeder 1; and

· Tree trimming covering Silay-Lopez Feeder 1.

Areas Affected:

LF1 Caneland (AIDSISA), Mansiguinon, Lantawan, Brgy. Guimbalaon, Brgy. Kapitan Ramon, Brgy. Patag

NGCP, CENECO Set Power Interruptions on Aug. 15-16

The National Grid Corporation of the Philippines (NGCP) is scheduling a power service interruption along Calumangan-San Enrique 69kV transmission line on August 15, 2015, Saturday, from 8:00AM to 5:00PM.

Central Negros Electric Cooperative, Inc. (CENECO) shall take advantage of this downtime by implementing simultaneous maintenance activities.

Date: August 15, 2015 - Saturday

Time: 8:00AM to 5:00PM

Reasons:

· NGCP will conduct replacement of rotten 69kV poles along Calumangan - San Enrique 69kV transmission line section; and

CENECO Sets Power Interruption on July 10, 2015

Central Negros Electric Cooperative, Inc. (CENECO) informs its electricity consumers that, in order to ensure stability of its distribution lines, maintenance activities will be conducted tomorrow, July 10, 2015, Friday, as follows:

Date: July 10, 2015 - Friday

Time: 6:00AM to 4:00PM

Reasons:

· Midspan erection of one 35 feet concrete pole and installation of three 25kVa private distribution transformers together with accessories and service wire;

· Tree trimming covering Mountain View Feeder 3; and